In this article
- What actually arrives with an invitation
- The first hour: deciding whether to chase it
- Reading the instructions to bidders first
- The site visit, and whether it is mandatory
- How the question period works
- Addenda, and the acknowledgement that trips people up
- Assembling the number without losing the thread
- Filling in the bid form exactly as asked
- Submitting, and the last hour
- Bid shopping, and what it does to your number
- After the deadline
- Frequently asked questions
An invitation to bid arrives as an email with links, a deadline, and an implication that everyone else already understands the process. Most painters respond to their first few badly, not because their pricing is wrong but because they treat a formal bid like a homeowner enquiry. The two work nothing alike.
The wider question of how to price this kind of work is covered in how to bid commercial painting jobs, and how to get invited in the first place is in how to get painting jobs from general contractors. This is about what to do in the two weeks after the invitation lands.
What actually arrives with an invitation
An invitation is a bundle rather than a document. Expect a covering letter or email naming the project, the scope you are being invited to price, and the deadline. Expect access to a drawing set and a specification, usually through a plan room or a shared folder rather than as attachments.
Expect a bid form, which is the sheet your number goes on. Expect instructions to bidders, which set out how the bid must be submitted and what happens if it is not. On public work expect requirements about bonds, wage rates and eligibility. And expect a list of addenda, which may be empty on day one and will not be by the deadline.
Pull everything down on the first day, including the files that look irrelevant. Plan rooms expire, links break, and being unable to open the specification three days before the deadline is an avoidable way to lose a bid.
The first hour: deciding whether to chase it
Not every invitation deserves a bid. Estimating is expensive, and a painter chasing everything prices badly because there is never enough time to price anything properly.
Five questions answer it quickly. Is the work the kind you actually do well. Is the timing compatible with what you already have booked, which is a capacity question rather than an optimism question, as painting business capacity planning sets out. Are the bonding and insurance requirements ones you can meet. Do you know who else is bidding and roughly how many. And is there anything in the documents that disqualifies you outright, such as an approved applicator requirement.
If the answer to any of the first four is uncomfortable, declining early is not a failure. It is the decision that protects the bids you do submit. Say no politely and promptly, because a fast no is remembered better than a late no bid.
Reading the instructions to bidders first
The instructions are the rules of the competition and they are enforced literally. They tell you the format, the delivery method, the deadline to the minute, whether alternates are required, whether the bid must be on the supplied form, and whether anything must be enclosed with it.
Bids get rejected for failing these rules while containing the best price in the room. Submitting on your own letterhead when the form was mandatory, omitting a required acknowledgement, or arriving four minutes late are all fatal in a formal process and all entirely avoidable.
On federal work the procedures are published rather than improvised, and reading them once gives you the shape of every formal process you will meet afterwards. The rules for sealed bidding are set out in the solicitation procedures, and current opportunities are listed at the federal contract opportunities system.
The site visit, and whether it is mandatory
Many invitations include a pre bid meeting or site walk, and the word to look for is mandatory. Where attendance is mandatory, a bid from a non attendee is not considered, full stop.
Even where it is optional, go if the building exists. You will learn things no drawing carries: the real substrate condition, access, parking, how far the material has to be carried, whether the building will be occupied, and what other trades will be doing around you. On refurbishment work that visit is worth more than any other hour in the bid period.
Ask questions there, but understand that verbal answers at a site walk are usually not binding. If an answer matters, submit it in writing afterwards so it comes back as an addendum.
How the question period works
There is a window during which bidders may submit questions, and it closes before the bid deadline. Questions submitted through the stated channel are answered formally and the answers are issued to every bidder, which is the point: the process is designed so nobody gets private information.
Use it. A well aimed question resolves an ambiguity that would otherwise sit in your price as a risk allowance, and the answer becomes part of the contract documents. A painter who asks nothing is either carrying every ambiguity or ignoring it.
Word questions neutrally and specifically. Point at the document, the sheet or section, and the ambiguity, and ask for a decision rather than an opinion. Do not use the question period to argue that the specification is wrong.
Addenda, and the acknowledgement that trips people up
An addendum is a formal change to the bid documents issued during the bid period. It can add scope, change a product, extend the deadline or answer questions. It is binding whether or not you read it.
Two rules. Check for new addenda every day, including the morning of the deadline, because late addenda are normal and a bid priced on superseded documents is either wrong or void. And acknowledge every addendum on the bid form exactly as instructed, because failure to acknowledge is one of the most common technical rejections there is.
When an addendum lands late and changes something material, ask for an extension rather than guessing. Asking is normal and frequently granted, since the same problem is affecting every bidder.
Assembling the number without losing the thread
Work the takeoff, then the labour, then the materials, then the project specific costs that only exist because this is formal work: submittals, mock ups, bonds, temporary protection, out of hours access, and the administrative time to run the paperwork. Those last ones are the ones a residential estimating habit leaves out.
Keep the base bid clean and put everything conditional somewhere else. Alternates go where the bid form asks for them. Unit rates go where the form asks for those. Assumptions go in your clarifications. Mixing the three into one number produces a bid nobody can compare, and a bid nobody can compare is a bid that gets set aside. The mechanics are covered in painting bid alternates and unit prices, and the wording in painting bid exclusions and clarifications.
Filling in the bid form exactly as asked
Use the supplied form. Complete every field, including the ones that seem redundant. Write the figure in both words and numerals if the form asks for both, and make sure they agree, because where they disagree the written words usually govern.
Sign it in the way the form specifies and by somebody authorised to bind the company. Attach whatever must be attached, in the order listed. Then read the instructions once more against what you have assembled, as a checklist rather than as prose.
Submitting, and the last hour
Submit early. The deadline is a hard boundary in a formal process, and the last hour is when portals slow down, files fail to upload and printers jam. A bid submitted the previous afternoon is a bid that cannot be lost to a technical failure.
Where a physical submission is required, allow for traffic, parking and finding the right office. Where it is electronic, upload well ahead and confirm you have a receipt.
Have somebody else check the form before it goes. Not the arithmetic, which you have already checked, but the mechanical things: that the figure in words matches the figure in numerals, that every addendum is acknowledged, that the signature is on the right line, and that the attachments listed are actually attached. Those are the errors an estimator who has been staring at the same document for a week cannot see, and they are the ones that void bids.
Keep a complete copy of exactly what you submitted, including the version of every document you priced from. If a dispute about scope arises later, the record of what you were looking at when you priced it is the thing that settles it.
Bid shopping, and what it does to your number
Bid shopping is the practice of taking your price to a competitor and asking them to beat it, after bids have been submitted. It is widely disliked, it is not generally illegal on private work, and it happens.
The signs are recognisable. A contractor who calls after the deadline to say you are close but not quite there, without naming a scope difference. A request to sharpen the number with no change to what is being asked for. A long delay followed by an approach on the same job at a lower figure.
The defence is not indignation, it is documentation and discipline. Price the job properly, submit a clear scope with your qualifications attached, and hold the number unless the scope changes. A painter who drops a price when asked, without anything changing, has taught that contractor how to buy from them permanently, and the same lesson applies whether the pressure comes from a builder or a homeowner.
Where a genuine scope difference is the reason, ask what it is. A specific answer lets you reprice honestly and sometimes wins the job. A vague answer is the tell, and the right response to it is a polite restatement of your price.
Public work is generally structured to prevent this, which is one of the underappreciated advantages of bidding it: the process is rigid, the results are published, and the number you submitted is the number that gets compared.
After the deadline
Formal processes announce results, sometimes publicly. Ask where you came, and ask what the spread was. Losing by a small margin against a competent field is useful information. Losing by a wide margin usually means you priced a different job, which is a scope reading problem rather than a pricing problem, and it is worth finding out which.
Following up on a formal bid is different from following up on a homeowner estimate, and the approach in how to follow up on a painting estimate needs adapting: with a general contractor the useful conversation is about the next project, not about revisiting this one.
Track your outcomes over time as one of the numbers you actually watch, in the way painting business KPIs describes. A bid that is never analysed is a cost with no return.
The bid deadline does not move. Your estimate can be faster.
PaintPricing builds the base bid, the alternates and the unit rates from one set of numbers, so a late addendum is a revision rather than an all nighter. Free for your first 3 quotes, no card required.
Frequently asked questions
Can I submit a bid that differs from what was asked for
Only if the instructions permit alternatives, and even then submit a compliant base bid alongside it. A bid that answers a different question is easy to set aside, however good the number is.
What if I spot an error in the documents after I submit
Tell them immediately and in writing. Some processes allow withdrawal or correction before award where a genuine error is demonstrated. Staying quiet and hoping is the worst of the options, because the error does not go away, it just becomes yours.
How many invitations should I be bidding
Fewer than you are invited to. Track how many bids it takes you to win one, and how long each takes to prepare, and the right number becomes an arithmetic question rather than a temperament one.
Do I need a bond to bid
On public work usually yes, and on larger private work sometimes. The requirement will be stated in the instructions, and it needs arranging before the deadline rather than after, and the surety side of it is covered in how to get bonded for commercial painting jobs.
Is it worth bidding when I do not know the competition
Sometimes, but treat an unknown field as a reason to price your own job properly rather than to guess low. Bidding against an imagined competitor is how competing with lowball painting bids turns into a race you did not need to enter.
What do I do with the takeoff if I lose
Keep it. The same building will be repainted, the same contractor will invite you again, and your own historical takeoffs are the fastest way to sanity check a future one. They are also the raw material for improving your production rates.
Finding public work, registering for it and reading the published bid results are covered in government painting contracts.